Lien waivers and lien releases in Washington:
what to get before the final payment

WHAT LIEN RELEASE SHOULD I GET FROM MY CONTRACTOR IN WASHINGTON?

A signed release from each major sub and supplier

A lien waiver or release is a signed paper saying a contractor, subcontractor or supplier has been paid and gives up its lien rights for that work. L&I tells homeowners to get a signed lien release from all major contractors, subcontractors and suppliers before the final payment, and offers a sample "Waiver of Lien" form (F625-029-000). Under RCW 60.04.071, once a claimant is paid it must sign a release when you ask.

General information, not legal advice. For a large project, have a lawyer review the release wording.
Illustration of three signed lien release forms, a check with two payees and house keys on a porch table.
Illustration. Collect releases from each sub and supplier before the final payment.

Why you need lien releases

How to collect releases, step by step

  1. Ask for the list. Before work starts, ask your contractor who its subs and major suppliers will be. On jobs over $5,000, the contractor must post a notice at the site that lists them (RCW 60.04.230).
  2. Keep every Notice to Owner. Anyone who sends one is a company you need a release from: see Notice to Owner.
  3. Pay with joint checks. L&I recommends checks payable jointly to the contractor and the sub or supplier.
  4. Collect signed releases on L&I's sample Waiver of Lien form or a similar document, one from each company, before the last payment.
  5. Consider escrow for a large job. L&I suggests asking whether the escrow agent protects you against liens when it pays out.
PaymentWhat to collect
Progress paymentRelease for work paid so far from the contractor; joint check if a Notice to Owner arrived
Final paymentSigned releases from the contractor and all major subs and suppliers
Retainage, if you held some backReleases first, then release the retainage
Based on L&I, What you should know about liens and Facts about construction liens (F625-017-000), and the RCW 18.27.114 disclosure on retainage.

If a release is refused or a lien is filed

Frequently asked questions

What is a lien waiver?

A signed document in which a contractor, subcontractor or supplier confirms payment and gives up lien rights for that work. L&I offers a sample Waiver of Lien form, F625-029-000.

When should I ask for lien releases?

Before the final payment. L&I says to get signed releases from all major contractors, subcontractors and suppliers on your project.

Does my contractor have to give me lien releases?

The required disclosure statement says you may request them, and L&I says the contractor must explain lien release documents if you ask. Once a claimant is paid, it must sign a release on request.

What is a joint check?

A check payable to both your contractor and a subcontractor or supplier, so both must sign it. L&I recommends it to make sure subs and suppliers get paid.

What if a paid company won't sign a release?

Under RCW 60.04.071, a court that finds the delay unjustified can award costs, attorneys' fees and damages.

Sources

  1. L&I — What you should know about liens
  2. L&I — Facts about construction liens (F625-017-000)
  3. Chapter 60.04 RCW — Mechanics' and materialmen's liens
  4. RCW 18.27.114 — Disclosure statement
  5. WashingtonLawHelp — Before you hire a contractor

Sources accessed November 24, 2026.

This guide summarizes state law and L&I information. It is not legal advice. See our disclosure and disclaimer.