Got a "Notice to Owner" in Washington?
What it means and what to do

WHAT IS A NOTICE TO OWNER IN WASHINGTON?

It is not a lien, but take it seriously

A "Notice to Owner" (notice of right to claim a lien) comes from a supplier or lower-tier subcontractor who wasn't hired by you. RCW 60.04.031 requires it before that company can enforce a lien. The form itself says "This is not a lien" and "Protect yourself from paying twice." On a remodel of a home you live in, such a claim can be paid only from money you hadn't yet paid your contractor when you received the notice. L&I says to stop further payments until you get lien releases.

General information, not legal advice. If a lien has already been recorded, talk to a lawyer.
Illustration of a mailbox holding a Notice to Owner letter, a stack of invoices, a check and a clipboard, with a house under remodel behind.
Illustration. A Notice to Owner is not a lien: pause payments, use joint checks and ask for releases.

Who sends a Notice to Owner

WhoMust send a notice?
The contractor you hired directlyNo
Subcontractor hired directly by your contractorUsually no; on a home you live in, the notice rule in subsection (3) can apply
Material and equipment suppliers you didn't hireYes
Lower-tier subs and design professionals you didn't hireYes
Workers claiming only for their laborNo
RCW 60.04.031(1)–(3). On commercial and most projects, the notice protects work after a date 60 days before it was mailed; for a new single-family home, 10 days.

How much is at risk on a home you live in

What to do when you get one

  1. Don't ignore it. L&I says to tell your contractor you received it and ask how the sender will be paid.
  2. Pause payments. L&I says not to make further payments to your contractor until you get lien release documents from the sender.
  3. Pay by joint check. L&I recommends checks payable to both the contractor and the subcontractor or supplier.
  4. Get releases before the final payment from all major subs and suppliers: see lien waivers.
  5. Keep the notice with your contract and payment records.

If an actual lien is recorded

Frequently asked questions

Is a Notice to Owner a lien?

No. The required form says "This is not a lien." It tells you who is supplying your project and that they could claim a lien if they aren't paid.

Can I end up paying twice?

That is the risk the notice warns about. On a remodel of a home you live in, claims from those you didn't hire are limited to what you hadn't yet paid your contractor when you got the notice.

Should I keep paying my contractor after a Notice to Owner?

L&I says not to make further payments until you get lien release documents from the sender, and to use joint checks.

Who doesn't need to send a Notice to Owner?

Anyone who contracted directly with you, workers claiming only for labor, and usually subcontractors hired directly by your prime contractor.

How long does a supplier have to file a lien?

It must record the lien within 90 days after it stopped furnishing materials or work, and send you a copy within 14 days.

Sources

  1. RCW 60.04.031 — Notices and exceptions
  2. Chapter 60.04 RCW — Mechanics' and materialmen's liens
  3. L&I — What you should know about liens
  4. L&I — Facts about construction liens (F625-017-000)
  5. L&I — Problems with a contractor

Sources accessed November 24, 2026.