DOES A CONTRACTOR NEED A WRITTEN CHANGE ORDER TO CHARGE MORE IN WASHINGTON?
A change order is a written agreement that changes the work, price or schedule in your original contract. L&I tells homeowners to make sure all change orders are in writing and to agree before work starts on how changes will be handled. In Seattle, changes to work shown on an issued permit also need SDCI approval first. Before you sign, check the new price, the new end date and whether sales tax is included.
What a change order should say
| Item | Why it matters |
|---|---|
| What is added, removed or changed | Avoids "that wasn't included" arguments later |
| Price change, plus or minus | The FTC says a change order can affect the project's cost |
| New schedule | The FTC says it can also affect the schedule |
| Sales tax | Washington sales tax applies to labor on home repairs: how it works |
| Signatures and date | Shows both sides agreed before the work was done |
L&I suggests your original contract describe its warranties and the process for change orders, and that you agree on a check-in plan for handling changes. See what a Washington home improvement contract should include.
Before you sign a change order
- Ask why. Is it something you asked for, a hidden condition found during work, or a missing item from the original bid?
- Compare with the contract. If the original scope already covered it, the price shouldn't go up.
- Permit changes. In Seattle, SDCI says changes to approved work during construction must be approved before you make them. Ask who will file the revision: see who pulls the permit.
- Don't pay ahead. Tie payment to finished work, as with the main contract: contractor down payments.
- Lien releases. If the change adds a new supplier or sub, ask for lien releases before final payment: lien waivers.
If the contractor demands more money mid-job
- A known red flag. The Washington Attorney General has warned that some scam contractors take money up front and then demand more once the job starts.
- Write it down. Reply in writing, ask for the reason and a written change order, and don't sign under pressure.
- If talks fail, try mediation, then small claims or a bond claim.
- If you end the job, see how to fire a contractor.
Frequently asked questions
What is a change order?
The FTC describes it as a written authorization for the contractor to change or add to the work in the original contract, which can affect the project's cost and schedule.
Do change orders have to be in writing in Washington?
L&I tells homeowners to make sure all change orders are in writing. Your contract may also require written, signed changes.
Can a contractor charge more than the estimate?
Only as your contract allows. Ask for a written change order that explains the reason, the new price and the new schedule before the extra work is done.
Do I need a new permit for a change?
In Seattle, SDCI says changes to approved work during construction need its approval first, through a permit revision.
Is sales tax charged on change orders?
Washington retail sales tax generally applies to home repair and remodel work, labor included, so a change order that adds work also adds tax.
Sources
- L&I — Hire Smart worksheet (F625-111-000)
- L&I — Hire smart step by step
- FTC — Hiring a Contractor
- Seattle SDCI — Building permit revisions
- Washington Attorney General — Warning on flood scams
- WashingtonLawHelp — Sue a construction contractor
Sources accessed November 24, 2026.
This guide summarizes agency information. It is not legal or tax advice. See our disclosure and disclaimer.