Contractor change orders in Washington:
extra charges, what to sign and what to refuse

DOES A CONTRACTOR NEED A WRITTEN CHANGE ORDER TO CHARGE MORE IN WASHINGTON?

Get every change in writing

A change order is a written agreement that changes the work, price or schedule in your original contract. L&I tells homeowners to make sure all change orders are in writing and to agree before work starts on how changes will be handled. In Seattle, changes to work shown on an issued permit also need SDCI approval first. Before you sign, check the new price, the new end date and whether sales tax is included.

General information, not legal advice. Your contract's change clause controls how changes are priced.
Illustration of a clipboard with a change order form listing scope, price and new date, a calculator and a pencil, with wall framing behind.
Illustration. A change order should be in writing, with the new price and schedule, signed before the work.

What a change order should say

ItemWhy it matters
What is added, removed or changedAvoids "that wasn't included" arguments later
Price change, plus or minusThe FTC says a change order can affect the project's cost
New scheduleThe FTC says it can also affect the schedule
Sales taxWashington sales tax applies to labor on home repairs: how it works
Signatures and dateShows both sides agreed before the work was done
L&I Hire Smart worksheet (F625-111-000) and Hire Smart step by step; FTC, Hiring a Contractor.

L&I suggests your original contract describe its warranties and the process for change orders, and that you agree on a check-in plan for handling changes. See what a Washington home improvement contract should include.

Before you sign a change order

If the contractor demands more money mid-job

Frequently asked questions

What is a change order?

The FTC describes it as a written authorization for the contractor to change or add to the work in the original contract, which can affect the project's cost and schedule.

Do change orders have to be in writing in Washington?

L&I tells homeowners to make sure all change orders are in writing. Your contract may also require written, signed changes.

Can a contractor charge more than the estimate?

Only as your contract allows. Ask for a written change order that explains the reason, the new price and the new schedule before the extra work is done.

Do I need a new permit for a change?

In Seattle, SDCI says changes to approved work during construction need its approval first, through a permit revision.

Is sales tax charged on change orders?

Washington retail sales tax generally applies to home repair and remodel work, labor included, so a change order that adds work also adds tax.

Sources

  1. L&I — Hire Smart worksheet (F625-111-000)
  2. L&I — Hire smart step by step
  3. FTC — Hiring a Contractor
  4. Seattle SDCI — Building permit revisions
  5. Washington Attorney General — Warning on flood scams
  6. WashingtonLawHelp — Sue a construction contractor

Sources accessed November 24, 2026.

This guide summarizes agency information. It is not legal or tax advice. See our disclosure and disclaimer.